Project Accounting Job Cost
Project Accounting
PRJ-AUTOMATION · Line Automation Upgrade
Job Cost report
Per cost code: Budget (budget lines) · Committed (open POs + subcontracts) · Actual (bills) · Forecast = Actual + Committed · Variance = Budget − Forecast (red = over budget).
| Code | Budget | Actual | Variance |
|---|---|---|---|
| 01 | 5,00,000 | 0 | 5,00,000 |
| 02 | 7,00,000 | 2,50,000 | 3,38,000 |
| 03 | 18,00,000 | 7,00,000 | 7,18,000 |
| 04 | 9,00,000 | 2,50,000 | 3,74,000 |
| 05 | 6,00,000 | 0 | 6,00,000 |
Assign cost codes
Pick a cost code per document to populate the report. Bills feed Actual; open POs and subcontracts feed Committed.
Open POs (committed) · 3
| Doc | Amount | Cost code |
|---|---|---|
| PO-2026-000009 | BDT 3,82,000.00 | 03 Equipment & machinery |
| PO-2026-000008 | BDT 2,76,000.00 | 04 Electrical & controls |
| PO-2026-000006 | BDT 1,12,000.00 | 02 Civil works |
Job cost: what you planned, promised, spent and expect to spend
For each cost code, one row shows the budget, what is committed on open orders, what has actually been billed, the forecast to the end and the variance. Red means over budget.
Now onboarding companies in Dhaka.
The five columns, in the order money moves
Every row follows the life of a cost: planned, promised, spent, and what it will end up as.
01 · Budget
What you planned
The total of the budget lines for the cost code.
02 · Committed
What you promised
Open purchase orders and subcontracts. The money is not spent yet, but it is owed.
03 · Actual
What you spent
Supplier bills tagged to the cost code. Forecast is actual plus committed, and variance is budget less forecast.
How the report gets its numbers
- Bills
- Each bill is tagged to a cost code and feeds Actual.
- Purchase orders
- Open orders feed Committed until they are billed.
- Subcontracts
- Subcontract commitments feed Committed in the same way.
- Budget lines
- Budget comes from the lines set up for each code.
- Variance in red
- A negative variance, over budget, is shown in red.
Job cost is where plans meet bills
It holds nothing of its own. It reads the budget, the open orders and the bills, grouped by cost code.
What feeds it
What follows it
Job costing for projects that buy before they build
Most of a project’s cost is promised on purchase orders long before the bill. Seeing committed cost is how you avoid being surprised.
Committed cost, not just spent
An approved order counts the day it is placed, not the day it is billed.
A forecast you can trust
Actual plus committed is what the code will cost if nothing else is ordered.
Assign as you go
Pick the cost code for each bill and order right in the page.
Red when over
A cost code that is forecast over budget stands out.
One purchase order, from order to actual
A sample equipment order, the way it usually runs.
A purchase order for 3,82,000 taka is approved.
It is assigned to cost code 03, and Committed rises.
The goods arrive.
The bill is entered, and the amount moves from Committed to Actual.
The forecast and variance are reviewed.
How different trades use job cost
- Retail
Fit-out costs against the estimate.
- Food & Hospitality
Build-out costs by area.
- Real Estate
Cost by phase and trade, with open orders.
- Consulting
Cost by deliverable.
- Manufacturing
Capex cost by equipment and installation.
- Health & Fitness
Equipment and fit-out costs.
- Trades
Cost by job, with parts ordered.
- Others
Cost by programme activity.
Questions we get about job cost
What is committed cost?
Open purchase orders and subcontracts that are agreed but not yet billed.
What is forecast?
Actual plus committed.
What is variance?
Budget less forecast. Red means the code is forecast to go over budget.
How do I get numbers into the report?
Assign a cost code to each bill, order and subcontract.
Are all purchase orders listed?
Orders are listed company-wide. Assign the ones that belong to this project.
Where is Adon ERP available?
We are currently onboarding companies in Dhaka. Book a demo and we will walk through a sample project with you.
Bring a few open purchase orders. We will assign them and read the report in the demo.
A live demo in English or Bangla, using sample books close to your own trade, with time for your accountant’s questions.